HWS Laboratory Event Log
1/9/09 Data base HWS officially begins at 16:45 PM. Using SRCC draw profile.
1/12/- 1/15/2009 Shake down process in progress. Flow meters replaced on tankless systems.
1/15/2009 Adjustment to ICS thermostat to match other systems
1/28/09 HWS Lab dedication ribbon ceremony with Bob Hasset DOE
2/2/09 Updated program to ASHRAE 90.2 draw profile
2/5/09 Adjustment to program draw events to keep draws at less than 65 gpd
3/2/09 Pipe insulation to electric, differential, ICS and PV pumped finished.
3/10/09 Insulation completed to all systems (early afternoon)
3/28/09 Begin testing new program to calculate parasitic energy for differential and gas tankless
3/30/09 Program now includes final version of parasitic energy consumption
4/22/09 Adjusted thermostat setting on tankless to slightly lower temperature. Left power breaker to OFF position, no performance data for rest of day.
4/23/09 Turned electric tankless system breaker to ON position
4/25/09 Problem with relay stuck on Takagi tankless. Additional Natural GAS consumption , No Btu’s logged which explained the low efficiency.
5/11/09 Tankless electric adjusted slightly down to lower temperature and energy output. Power breakers were left to OFF position, no performance data for rest of day
5/12/09 Tankless electric breaker back ON at 10:00 AM
5/18/09 Download to CR10X logger/controller program with Building America/NREL May hot water draw profile.
5/19/09 Corrected program, BA_May version officially begins at 9:30 AM
5/27/09 Tankless electric unit replaced with current production unit. Unit thermistors calibrated by manufacturer at FSEC. Tested with draw at 2:35 PM. Thermostat adjustment up slightly at 4:30 PM.
6/1/09 ASHRAE 90.2 Draw proifle program downloaded to CR10X at 4:50 PM. Very fine adjustments made to flat plate solar collector tank thermostats. Adjusted mixing valve slightly (lower settting) on Solar PV system.
6/15/09 Download to CR10X logger/controller program with Building America/NREL June hot water draw profile.
6/26/09 Natural gas 40 gal. system down 6/25 for water inlet distribution manifold leak repair. Schedule on all other systems disrupted 6/26 between 9:30 and 12:30 PM. Operation restored on NG 40 gallon tank at 3:30 pm.
7/1/09 ASHRAE 90.2 Draw proifle program downloaded to CR10X at 11:36 AM.
7/16/09 Download to CR10X logger/controller program with Building America/NREL JuLY hot water draw profile schedule.
8/3/09 ASHRAE 90.2 Draw proifle program downloaded to CR10X at 3:25 PM.
8/21/09 Download to CR10X logger/controller program with Building America/NREL August hot water draw profile schedule.
9/4/09 ASHRAE 90.2 Draw proifle program downloaded to CR10X at 1:50 PM.
9/18/09 Download to CR10X logger/controller program with Building America/NREL September hot water draw profile schedule.
9/30/09 Problem with flowmeter in morning hours draw schedule preventing log of BTU's, resulting in lower daily efficiency.
10/05/09 Flowmeter replaced on ICs/50 Gal. system due to failure. Previous two days (weekend) No BTU data. Changed to ASHRAE 90.2 draw schedule in the afternoon.
10/19/09 Download to CR10X logger/controller program with Building America/NREL October hot water draw profile schedule. Replaced freeze valve on Diff. Solar system
10/14 - 10/14/09 Natural Gas tank meter went thru a series of fixes. Good known data leading to Eff=0.56 begins on Oct. 15, 2009
10/20 - 10/22/09 Flat plate PV system down, check valve removed and cleaned, air shred valve adjusted, solenoid valve replaced. Last good Eff = 1.8 on Sat. 10/17.
11/2/09 ASHRAE 90.2 Draw proifle program downloaded to CR10X at 11:00 AM.
11/16/09 Download to CR10X logger/controller program with Building America/NREL November hot water draw profile schedule at 10:00 AM.
11/23 THRU 11/24/09 Gas line rupture, no gas service, pilot light restored morning of 11/24/09. Discard 11/23 & 11/24 data. Good data on gas systems begins 11/25/09.
12/2/09 ASHRAE 90.2 Draw proifle program downloaded to CR10X at 1:45 PM.
12/8/09 Increased thermostat setting on electric tankless water heater at 4:00 PM.
12/16/09 Downloaded to CR10X logger/controller program with Building America/NREL December hot water draw profile schedule.
1/4/10 ASHRAE 90.2 Draw proifle program downloaded to CR10X at 2:30 PM.
1/6/10 Re-positioned pulser mechanism on tankless nat. gas system due to missed pulses on 1/5/10. Effciency on tankless gas on these two days is higher due to missed pulses.
1/15/10 Replaced PV pump with new D5 Solar 090B. Use only Jan 16 & 17 for ASHRAE TOD analysis.
1/19/10 Downloaded NREL/BA January Draw profile program to CR10X at 11:30 AM.
2/1/10 Downloaded ASHRAE 90.2 Draw profile program to CR10X at 9:45 AM.
2/15/10 Downloaded NREL/BA February Draw profile program to CR10X at 2:30 PM.
3/1/10 Downloaded ASHRAE 90.2 Draw profile program to CR10X at 9:30 AM.
3/15/10 Downloaded NREL/BA March Draw profile program to CR10X at 10:30 AM.
4/1/10 Downloaded ASHRAE 90.2 Draw profile program to CR10X at 9:30 AM.
4/15/10 Downloaded NREL/BA April Draw profile program to CR10X at 1:50 PM.
4/1/10 Multiplexer channel problem for the tankless electric. Only six days of good data for this system during April
5/3/10 Downloaded ASHRAE 90.2 Draw profile program to CR10X at 4:30 PM.
5/10/10 System in partial shut-down mode to save water/energy during reconfiguration.Solar systems generating hot water without aux. heat. Recording baseline data
5/26/10 Ten watt photovoltaic module removed from Solar flat plate PV-DC pump system. Replaced with a new 20-Watt module.
5/27/10 Stagnant PV solar flat plate system (no hot water circulation). Flush to purge air from system to allow full pumping circulation.
6/22/10 Heat Pump Water Heater was connected and started on Default Hybrid Mode. Initial 2.6 Amps @ 10:50AM, 2.9 Amps at 11:50. Shed temp 87.1 F HP discharge air temp 67.5 F.
******************* Phase 2 *********************
All systems under ASHRAE 90.2 (64.3 gpd) draw profile schedule.
6/22/10 Heat Pump Water Heater was connected and started on Default Hybrid Mode. Initial 2.6 Amps @ 10:50AM, 2.9 Amps at 11:50. Shed temp 87.1 F HP discharge air temp 67.5 F.
6/23-6/30/10 Disconnected bottom element to 50 gal on ICs system. A series of thermostat adjustments were made to bring water temperature to ~120 F.
7/1/10 Replaced flow regulator on reference 50 gal. electric water heater.
7/1-7/2/10 Replaced flow regulator on Pv flat plate solar system and installed new SID20 pump with 20 Watt PV panel.
7/6/10 Lowered thermostat setting on ICs/50 gal. system due to 128 F delivery temperature deviation shown on July 5th resulting in higher electric demand (6.9 kwh).
7/14/10 Heat Pump Condensate measurement added (ch 53) at 4:30 PM -- grams of water.
7/30/10 HWS Lab Relative Humidity (RH%) sensor added at noon (12:00 pm), installed on north wall at 56 inches from floor (about same height as HP compressor).
8/9/10 Turned ICS/50 gallon tank upper element thermostat up a notch (...having trouble dialind 125F setpoint).
8/12/10 Installed 2nd 20W PV module (now 40 watt) to SID20 pump with string diode arrangement for overvoltage protection.
8/16/10 Adjusted ICS/50 gallon upper element thermostat up again. Made adjustment to PV pumped system mixvalve down slightly.
9/10/10 Begin standby loss testing on Nat. gas 40 gallon tank.
9/14/10 Repositioned gas meter pulset at ~1:30 PM.
9/17/10 Downloaded new HWS_SEP_HP.csi program to logger at 5:14 PM.
9/22/10 Thermostat set to ~130 on Nat. gas tank.
9/27/10 R-11? wrap installed over electric 52 gallon reference tank. Thermostat setting remains same ~120F.
10/4/10 Downloaded ASHRAE 90.2 DRAW schedule program to logger at 11:00 AM.
10/11/10 R-11? wrap removed from electric 52 gallon reference tank (late afternoon).
10/21/10 Downloaded NREL/BA draw schedule HWS_OCT_HP.csi program to logger at 4:45 PM.
11/1/10 Downloaded ASHRAE 90.2 draw schedule program to logger at 10:00 AM. Replced flow regulator to Diff. controlled solar ssystem.
11/17/10 Tankless Nat. Gas turned OFF for flush pump preparations.
11/18/10 Tankless Nat. Gas was flsuhed with white vinegar for 2 hours to flush heat exchanger.
11/22/10 Downloaded NREL/BA draw schedule HWS_NOV_HP.csi program to logger at 11:00 Am.
12/3/10 Downloaded ASHRAE draw schedule Program to logger at 4:30 Pm.
12/20/10 Downloaded NREL/BA draw schedule HWS_DEC_HP.csi program to logger at 4:45 PM
1/5/11 Downloaded ASHRAE draw schedule Program to logger at 11:30 am.
1/12/11 P/T Valve leaks on heat pump noticed.
1/14/11 P/T Valve leaks on heat pump. 163.5grams of water over 24hr period.
1/18/11 Downloaded NREL/BA draw schedule Program to logger at 4:30 Pm. Installed/test differential controller to PV solar system
1/21/11 Installed Differential controller to Solar Flat Plate PV pump System.
2/1/11 Downloaded ASHRAE draw schedule Program to logger.
2/4/11 Begin ICS/50 tank thermosat adjustment to lower temperature.
2/14/11 Downloaded NREL/BA draw schedule Program to logger at 3:00 Pm.
3/2/11 Heat Pump water draw malfunction on logger controls-- troubleshoot starts (see 3/8/11)
3/3/11 Downloaded ASHRAE draw schedule Program to logger at 10:00 am.
3/4/11 Flow meter replaced on Heat Pump Water heater, removed check valve out of incoming city water (cold inlet).
3/8/11 Trouble shoot all day found short on flow meter line caused by heat shield during solder of copper piping.
3/17/11 Downloaded NREL/BA draw schedule Program to logger at 4:00 PM.
4/1/11 Downloaded ASHRAE draw schedule Program to logger at 11:00 am.
4/15/11 Downloaded NREL/BA draw schedule Program to logger.
5/2/11 Downloaded ASHRAE draw schedule Program to logger.
5/17/11 Downloaded NREL/BA draw schedule Program to logger at 3:00 pm.
6/1/11 Downloaded ASHRAE draw schedule Program to logger AT 4:15PM. Expansion Tank removed from Solar differential system.
6/2/11 Downloaded NREL/BA draw schedule Program to logger at 4:30 for further testing post removal of expansion tank.
6/8/11 Secondary flowmeter on Differential controlled solar system was replaced with pos. displacement meter at 4:00 PM.
6/10/11 Removal of expansion tanks on both PV pumped and ICS/50 solar systems at 9:30 AM.
6/13/11 Secondary flowmeter on PV Pumped solar system was replaced with pos. displacement meter at 3:00 PM.
6/16/11 Differential Solar system repairs end (6/9- 6/14). Good data resumes June 15.
6/17/11 Flow regulator replaced on Tankless Nat. Gas system at 2:30 PM.Clogged regulator cause limited firing on unit for previous 12 days.
6/23/11 Flow meter calibrations 10:AM - 5:00PM. Flow regulator replaced on PV solar system and Standard 50 gal waer heater.
6/24/11 Flow meter calibrations continue 10:AM - 4:00PM.
6/27/11 Expansion tanks on two solar flat plate systems re-installed for test.
6/28/11 Expansion tanks on two solar flat plate systems removed at 4:30 PM. Solenoid replaced on 50 gal. electric water heater.
7/15/11 Downloaded NREL/BA draw schedule to logger at 4:30pm.
8/1/11 Removed insulation from ICS collector at 9:45AM. Downloaded Ashrae draw schedule to logger at 4:00pm.
8/16/11 Downloaded NREL/BA draw schedule to logger at 4:30pm.
8/18/11 Replaced flow regulator on baseline electric 50 gal wth a cleaned used regulator.
9/6/11 Downloaded ASHRAE draw schedule to logger at 10:50 Am.
9/16/11 Downloaded NREL/BA draw schedule to logger at 4:30 Pm.
9/28/11 Failure with HPWH inlet temp sensor
10/5/11 Downloaded ASHRAE draw schedule to logger at 4:45 pm.
10/19/11 Measured HPWH airflow (130 cfm). Downloaded NREL/BA draw schedule to logger at 4:45 Pm.
10/24/11 Replaced Multiplexer with a new one (morning)
10/28/11 Enclosed HPWH in 92.5 cu.ft. space around 4:30 PM
11/7/11 Removed HPWH closet enclosure at 9:00 AM
11/10/11 Downloaded ASHRAE draw schedule around 4:30 PM
11/18/11 Downloaded NREL/BA draw schedule at 2:50 PM
12/8/11 Downloaded ASHRAE draw schedule at 10:30 AM
12/15/11 ICS/50 + HPWH installed Now system #3 (No power 'til Dec 19); Std 50 gal electric installed Now system #7 (no power until 12/20)
12/20/11 First full data for ICS/50 + HPWH hybrid system
12/21/11 Downloaded NREL/BA draw schedule at 10:50 AM; Installed cap + wrap to standard 50 gal electric (sys #7)
******************* Phase 3 ***************************
12/15/11 ICS/50 + HPWH installed Now system #3 (No power 'til Dec 19); Std 50 gal electric installed Now system #7 (no power until 12/20)
12/20/11 First full data for ICS/50 + HPWH hybrid system
1/29/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
2/1/12 ******* FEBRUARY ***** BEGIN PHASE 3 HYBRID SYSTEMS AND NATRUAL GAS TANKLESS CONDENSATE
2/20/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE, Adjust Mixing valve on solar/tankless cond to #2 setting, Increase Airtap T'stat to 127 F on HPWH/solar retrofit system.
1/29/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
3/4/12 - 3/6/12 BAD DATA ON 50 GAL. ELECTRIC BASELINE HEATER. REPLACED SOLENOID ON 3/6 3:30 pm
3/6/12 DOWNLOADED NREL/BA DRAW PROFILE SCHEDULE FOR MONTH OF MARCH AT 4:00 pm
3/14/12 REPLACED FLOW REGULATOR ON HYBRID SOLAR HPWH SYSTEM#2; REPAIRED PLUMBING NO DATA LOST.
4/4/12 - Fixed wiring and valve problem on 40 gal. NG upright tank. Draws now reach expected quantities.
4/6/12 - DOWNLOADED NREL/BA SCHEDULE PROGRAM TO LOGGER AT 3:45 pm
4/11/12 - FIXED LEAK AND REPLACED FLOWMETER TO OUTDOOR TANKLESS HEATER AFTERNOON.
4/11/12 - DATA DISCARDED BETWEEN 11:15 - 12:45 PM DUE TO LEAK FIX ABOVE. COP CALC ON OUTDOOR TANKLESSS OK NOW.
4/12/12 - 4/19/12 TANKLESS OUTDOOR & CAP/WRAP SYSTEM BAD DATA COP WRONG
4/19/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
5/7/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
5/23/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
6/1/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
6/7 - 6/8/12 BAD DATA ON SYSTEM #6 COND TANKLESS
6/18/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
6/26/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
7/16/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
7/31/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
8/14/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
9/4/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
9/17/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
10/1/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
10/17/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
10/29/12 DISCONNECTED CONTROL VALVE ON SYSTEMS #1 AND #7
11/5/12 INSTALLED INSULATION JACKET OVER STD. 50 GALLON ELECTRIC REFERENCE TANK.
11/16/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
11/27/12 INSTALL T'COUPLE ON TANKLESS COND (OUTDOOR) AFTERNOON
11/30/12 ADJUSTED MIXVALVE TO MIN SETTING (1 =< 110 F) ON SOLAR-TANKLESS NG SYSTEM
12/3/12 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
12/5/12 REPLACED THERMOCOUPLE HOT OUTLET ON NG 40 GAL.
12/12/12 REPLACED THERMOCOUPLE HOT OUTLET ON 50 GAL electric & 50 galCapWrap.
12/20/12 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
1/7/13 DOWNLOADED ASHRAE DRAW PROFILE SCHEDULE
1/7/13 REPLACED LEAKY FREEZE PROTECT VALVE ON (HYBRID SOLAR/AIRTAP HP) FLAT PLATE SOLAR COLLECTOR
1/14/13 STD 50 GAL ELECTRIC BREAKER ON (OFF DURING WEEKEND)
1/15/13 DOWNLOADED NREL/BA PROFILE SCHEDULE
******************** Phase 4 ****************************
5/7/13 SYSTEMS INSTALLED - BEGIN NEW TESTING ROTATION
5/23/13 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
6/15/13 PARTIAL SYSTEMS DATA BEGINS
6/21/13 ADJUSTED BASELINE ELECTRIC THERMOSTAT TO MATCH CAP-WRAP TANK
6/24/13 ADJUSTED BASELINE NAT. GAS THERMOSTAT (PREVIOUS DAY 117F)
6/25/13 FOUND SMALL CHUNK OF MINERAL DEPOSIT IN SOLENOID VALVE, FIXED/REASSEMBLE VALVE ON BASELINE ELCTRIC.
7/7/13 FOUND LEAK ON ELECTRIC TANK W/CAPWRAP. NEW PYRANOMETER INSTALLED IN AFTERNOON
7/8/13 MICRO-ADJUSTMENT TO BASELINE ELECTRIC and SOLAR POLYMER TANK THERMOSTAT TO 120 F
7/19/13 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
8/2/13 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE
8/9/13 WRAPPED CAP/WRAP TANK. Water Turn Off/On/off/On ending at 6:58 AM
8/12/13 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
8/19/13 ADJUSTED NAT. GAS BASELINE THERMOSTAT DOWN TOWARDS 120F
8/12/13 PLUMBING WORK DONE ON POLYMER SOLAR SYSTEM WATER SHUT OFF AT 9:30 AM. DRAWS RESTORED AT 1:45 PM
8/28/13 Downloaded NREL/BA w/MIXVALVE CORRECTION TO SOLAR POLYMER TANK
8/29/13 ADJUSTED MIXVALVE TOWARDS 120 F AT 11:00 AM
8/29/13 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE. ADJUSTED NAT. GAS TANK uP SLIGHTLY.
9/12/13 PUMP STATION PERIPHERAL POWER METER INSTALLED ON SOLAR POLYMER SYSTEM
9/16/13 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE
9/19/13 Ar WRAP INSTALLED ON ELECTRIC 50 GALLON TANK AT 11:00 AM
10/2/13 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE AFTERNOON.
10/16/13 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE AFTERNOON.
11/1/13 DOWNLOAD ASHRAE DRAW PROFILE SCHEDULE AFTERNOON.
11/19/13 INFRARED PICTURES (1 MIN.) TAKEN ON AOSMITH HPWH
11/15/13 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE AFTERNOON.
12/2/13 DOWNLOAD ASHRAE90.2 DRAW PROFILE SCHEDULE IN MORNING.
12/13/13 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE AFTERNOON.
1/16/14 DOWNLOAD ASHRAE90.2 DRAW PROFILE SCHEDULE IN MORNING.
1/24/14 ADJUSTED NAT GAS HEATER T'STAT DOWN
1/27/14 ADJUSTED NAT GAS HEATER T'STAT AGAIN, FURTHER LOWER SETPOINT
1/31/14 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE.
2/16/14 DOWNLOAD ASHRAE90.2 DRAW PROFILE SCHEDULE.
2/11/14 INSTALLED TRIPLE CAP ON ELECTRIC TANK. FIRST FULL DAY DATA ON 2/12
3/3/14 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE.
4/4/14 DOWNLOAD NREL/BA DRAW PROFILE SCHEDULE.
4/17/14 DOWNLOAD ASHRAE 90.2 DRAW PROFILE SCHEDULE.
7/20/14 End of 120 F thermostat setting testing
|